|
Time frames for various types of applications are indicated below, including categories
for which the FTZ staff's goal is to process applications in significantly less time than
the 10 to 12 month regulatory time frames for Board action. However, it is important for all
parties to note that it is not possible to process an application for Board action in less
than 6 months because doing so would require shifting resources in a manner that would
unfairly delay the processing of applications from other companies or communities.
Note: The time frames cited here are from the date when the FTZ Board officially dockets
the application in question. Any time spent requesting from the applicant (or awaiting)
additional information needed for the application to meet the docketing standard inherently
does not fall within the time frames discussed here.
The specific time frames applicable to various application types are as follows:
|
Manufacturing Applications (including Subzones with Manufacturing Authority)
To assist U.S.-based manufacturing, the FTZ staff has established a goal of expedited
processing for manufacturing applications (that is, within 6 to 8 months from docketing,
which is significantly faster than the 12 month regulatory standard). This expedited
processing time depends on applicants' adherence to the standard application formats and on
no case issues arising.
|
GPZ Expansions/Reorganizations (incl. ASF) and Non-Manufacturing Subzones
The standard processing time is 10 months. We will make every effort to act upon public-
interest based requests for expedited processing relative to the 10 month regulatory
standard. Also, based on the relative simplicity of the analysis generally required, we have
established a goal of processing within 6 to 8 months ASF reorganization applications that
do not involve the addition of new Magnet sites.
|
Temporary/Interim Manufacturing Authority (T/IM)
T/IM applications are generally processed within 75 days of docketing. In order for a
T/IM application to docketed, the completed application along with a letter of concurrence
from the CBP Port Director must be submitted.
|
Minor Boundary Modifications
Requests for minor boundary modifications are generally processed within 30 days of the
receipt of a complete request. In order to be considered complete, the incoming request
must include all required elements: the grantee's letter, responsive answers to all of the
questions in the standard request format, all needed attachments (including map(s) and legal
descriptions) and a letter of concurrence from the CBP Port Director.
|